Underground Projects

Planned Finish
Funding
Estimate ($000)
Tumon 34.5 kV & 13.8 kV Underground Conversion Phase II
Jun-04
Tumon Beautification Bond Funds
FY' 06
FEMA 90%, GPA 10%
1,200
FY' 06
700
FY' 06
2,960
FY' 06
2,480
FY' 07
3,520
FY' 07
3,550
FY' 07
1,510
FY' 07
3,240
TOTAL INVESTMENT
19,160